• GMP fined more over Lowell wind equipment transport
    By
     | February 09,2013
     
    AP File Photo

    A truck hauls part of a wind tower in Lowell in August. Vermont utility regulators have fined Green Mountain Power $30,000 stemming from five violations of its permit to ship turbine parts to an industrial wind-power project last year.

    LOWELL — Vermont’s largest electric utility has been fined $30,000 by state utility regulators for violating the permit that governed the delivery by road of turbine parts used in the construction of the Lowell Mountain wind project.

    Green Mountain Power and the Public Service Department, which represents the state in utility issues, had agreed upon a fine of $7,500 for the violations that took place last summer when the turbine parts were delivered without giving proper notice to the communities through which the trucks carrying the parts passed.

    But the utility-regulating Public Service Board determined the fine wasn’t enough. The board increased the fine to $30,000.

    “We have determined that a higher penalty is warranted for violating the transportation plan,” said the board’s order.

    GMP spokeswoman Dorothy Schnure said Thursday that no property was harmed during the violations. And a New Hampshire company hauled wind turbine parts along the same route last summer without any requirements to warn Vermont officials.

    “We’re really disappointed that the Public Service Board chose this level of fine for an administrative oversight,” Schnure said. “We had a permit. We used the route for five days due to an administrative error on our part before we had completed all technical notifications and actions.”

    Most of the turbine parts used in the Lowell Mountain project were shipped from southern Vermont to Lowell and from Island Pond’s rail yards to Lowell, all without violations. But the utility made a handful of shipments from northern New York to Lowell.

    GMP asked for and received an expedited permit to use the northern route, but the utility did not get a waiver for a 30- to 60-day warning period for the towns through which the parts would be moved.

    The 21-turbine Lowell Mountain project started generating electricity late last year.

    MORE IN Vermont News
    MONTPELIER — Republican Scott Milne, the state GOP-backed candidate for the gubernatorial... Full Story
    State fire investigators ruled out arson as the cause for a massive fire that razed Rutland... Full Story
    Arson ruled out in Rutland Plywood blaze
    The State Board of Education is calling on Congress to rethink the testing policies of No Child... Full Story
    More Articles
  •  
     
    • MEDIA GALLERY 
    • VIDEOS
    • PHOTOS